|
Introduction | Frame shotblasting | Wheel tyre turning | Tender tank | Rear frame stretcher | Loco rear dragbox | Boiler Overhaul |
The boiler is the largest, and the most expensive item that needs overhaul before NG15 №134 can run again - it is the most vital piece as well!
This work has been contracted out to Locomotive Maintenance Services in Loughborough. They took the boiler as it was and have done a full inspection to agree a plan of work with the boiler inspector and the FR company. Once all parties were satisfied LMS will then overhaul the boiler and get it through its various boiler tests and certifications.
This exercise started in 2019 when the boiler was moved from Dinas to Loughborough.
The boiler at Dinas in 2009 (right) and in 2018 it being loaded at Dinas for transfer to LMS at Loughborough. (Photo: Chris Parry) (left).
Once at Loughborough the boiler was left until March 2021 when initial exploratory work was commenced to establish the true condition of the boiler and the work needed to restore back to operating condition. This consisted with a basic clean and some cutting away of platework so as its true internal condition could be assessed. With agreement reached between the various parties work commenced a few months later.
The
work has taken the form of first stripping out all wasted material and
adding patches as required. The foundation ring was also overhauled and
wasted material replaced before it was refitted.
Chalk
marks showing the extent of a typical patch needed to the boiler. Seen
in June 2021 (left)
and later in September whith the wasted material in the process of
being
replaced (right). (Photos: Adrian Strachan).
During
the assessment of the work needed, it was agreed with the boiler
inspector that as we were replacing the whole of the new front boiler
barrel section we could take the opportunity to move the dome position
further to the rear of the boiler.
This was to give a greater leeway of water levels in the boiler when
negotiating gradients in reverse, especially up the 1:40 gradient out
of
Beddgelert that it will have to do regularly in service on the WHR.
The new (and now longer to allow for the moved dome) font boiler barrel section. (Photos: Adrian Strachan).
As
well as new boiler material being needed, whether patches or a complete
barrel section, there were also a whole lot of new stays needed. The
stays were inserted and the repaired foundation ring riveted back in
place.
New stays being fitted in May 2022. (Photo: Adrian Strachan)
The
boiler continued to
mage good progress throughout the middle of 2022 to the result that it
was getting close to being a complete boiler again as can be
seen
in the photos below in July and then October 2022.
The new front boiler barrel section being trial fitted in July 2022 (left) and an almost complete boiler in October 2022. (Photo: Adrian Strachan)
Following
hydraulic testing in early November 2022 the boiler passed its steam
test in the presence the boiler inspector on the 14th November.
The boiler at its working pressure for the steam test. (Photos: Adrian Strachan).
There then followed a number of other steam tests to thermal cycle the boiler with any minor leaks being subsequently caulked. A final steaming took place in the week of Monday 9th January 2023 after which it was deemed fit to be released to the railway.
The
following Friday therefore, the boiler was transported from LMS in
Loughborough to Dinas in Wales.
The boiler having just arrived at Dinas, (left), and the boiler having its ashpan attached before being lowered into the frames, (right).
The
boiler was first brought down close to the frames so as the ashpan
could be attached, that after a bit of tweaking is subsequently did,
then the boiler was dropped into the frames. By this time it was
getting quite dark before the loco, the frames with boiler, were moved
inside the goods shed.
The loco being moved inside the goods shed, (left), and the loco now in the goods shed for the night, (right).
And finally a video of the boiler's arrival is available on the Ffestiniog and Welsh Highland Railway's YouTube Channel:
The boiler being delivered to Dinas and being fitted into №134's frames. |